恭城实习报告_大厂实习报告
三篇
在当下这个社会中,我们都不可避免地要接触到报告,我们在写报告的时候要避免篇幅过长。为了让您不再为写报告头疼,下面是小编帮大家整理的3篇,仅供参考,大家一起来看看吧。
篇1
学生姓名:
专业班级: 学 号: 指导老师:
桂林理工大学
目 录
第一章 绪
论 ·············································································
············ 3
1.1 实习目
的 ·············································································
········· 3
1.2 实习任
务 ·············································································
········· 3
1.3 完成工作量
及提交成果 ································································· 8
1.4 前人研究简
史 ·············································································
·· 10
第二章 区域地质
概
况 ·········································································· 12
2.1 区域地
层 ·············································································
········· 12
2.2 区域构
造 ·············································································
········· 15
2.3 区域岩浆
岩 ·············································································
······ 22
2.4 区域矿
产 ·············································································
农业银行客户经理述职报告
········· 27
第三章 测区地质
特
征 ·········································································· 29
3.1 地
层 ·············································································
················· 29
3.2 构
造 ·············································································
················ 32
第四章 基于3s地
质填图方法 ····························································· 40
4.1 基础底图的
数字
化 ········································································· 41
4.2 gps在地质
填图中的应用 ····························································· 44
4.3 rs在地质填
图中的.应用 ································································ 48
第五章 地质发展
史 ·············································································
·· 53
5.1 沉积发展
史 ·············································································
······ 53
5.2 构造发展
史 ·············································································
······ 55
第六章 结束
语 ·············································································
·········· 57
参考文
献···········································································
·········· 62 ? 附表一:实测地层剖面记录表
? 附表二:节理产
送别的诗句有哪些四年级
状统计表
? 附表三:gps点
数据属性表
? 附图一:广西灌
阳上泥盆统实测地层剖面图
? 附图二:节理走
向玫瑰花图
? 附图三:广西灌
阳地区区域地质纲要图
? 附图四:广西灌
阳地区区域底层柱状剖面图
篇2
专业:勘查技术与工程
姓名:王亚明
班级:勘查092
学号:16309207
实习时间:20xx.9
指导教师:谷复光
一.工程概况
川渝.鸿泰国际—环球贸易中心位于长春市净月开发区彩宇广场南侧。主楼结构形式为框剪结构,地下室为框架结构,总规模为158169.67㎡。基坑采用放坡开挖,支护方式为水泥土排桩支护,基坑降水采用井点降水法,由于工程荷载较大采用桩基础的人工挖孔灌注桩。施工单位为四川建设集团有限公司,监理单位为长春市建设监理公司。
二.实习目的
1. 通过到现场实习,真正理解在课堂上学习的知识,充分的将理论与实践相结合,为以后的工作学习奠定基础。
2. 熟悉钻孔灌注桩的施工流程及其荷载传递的特点与规律。
3. 通过实习认识基坑开挖方式、基坑降水流程、基坑排桩支护、基础施工等工艺流程。
4. 本次实习对于以后的毕业设计及在工作岗位将会起到一个过渡作用,对于桩基础的施工有一个认识与理解。
5. 丰富理论知识,锻炼自己的工程实践能力。
三.实习内容
门店转让合同正规版本
(一)基坑开挖
1.机械开挖应根据工程规范、地下水位高低、施工机械条件、进度要求等合理的选用施工机械,以充分发挥机械效率,节省机械费用,加速工程进度。
2.土方开挖应根据确定的开挖路线顺序、范围、基底标高、边坡坡度、排水沟、集水井位置以及挖出土方堆放地点等正确操作,尽量减少机械超挖和人工挖方。
3.大面积基坑底标高不一,机械开挖次序一般采取先整片挖至一平均高,然后再挖个个别较深部位。
4.基坑边角部位,机械开挖不到之处,应用少量人工配合清坡,将松土清至机械作业半径范围内,再用机械掏取运走,人工清土所占比例一般为1.5%-4%,修坡以厘米限制误差。
5.挖掘机、运土汽车进出基坑的运输道路,应尽量利用基础一侧,或两侧相邻基础以后开挖的部位,使它相互贯通作为车道,或者利用提前铲除土方后的地下设施部位作为相邻的几个基坑开挖地下运输通道,以减少挖土量。
6.如遇软土地基或雨期施工,进入基坑行走需铺垫钢板或铺路基箱垫道。
7.机械开挖应由深而浅,基坑及边坡应预留一层300㎜左右厚土层用人工清底、修坡、找平,以保证基底标高和边坡坡度正确,避免超挖和土层遭受扰动。
(二)基坑支护「水泥土搅拌桩」
1.设计要求 基坑支护作为一个结构体系,应要满足稳定和变形的要求,即通常规范所说的两种极限状态的要求,即承载能力极限状态和正常使用状态。所谓承载能力极限状态,对基坑支护来说就是支护结构破坏、
倾倒、滑动或周边环境的破坏,出现较大范围的失稳。一般的设计要求是不允许支护结构出现这种极限状态的。而正常使用极限状态则是指支护结构的变形或是由于开挖引起周边土体产生的变形过大,影响正常使用,但未造成结构的失稳。
因此,基坑支护设计相对于承载力极限状态要有足够的安全系数,不致使支护产生失稳,而在保证不出现失稳的条件下,还要控制位移量,不致影响周边建筑物的安全使用。因而,作为设计的计算理论,不但要能计算支护结构的稳定问题,还应计算其变形,并根据周边环境条件,控制变形在一定的范围内。
一般的支护结构位移控制以水平位移为主,主要是水平位移较直观,易于监测。水平位移控制与周边环境的要求有关,这就是通常规范中所谓的基坑安全等级的划分,对于基坑周边有较重要的构筑物需要保护的',则应控制小变形,此即为通常的一级基坑的位移要求;对于周边空旷,无构筑物需保护的,则位移量可大一些,理论上只要保证稳定即可,此即为通常所说的三级基坑的位移要求;介于一级和三级之间的,则为二级基坑的位移要求。
对于一级基坑的最大水平位移,一般宜不大于30mm,对于较深的基坑,应小于0.3%H,H为基坑开挖深度。对于一般的基坑,其最大水平位移也宜不大于50mm。一般最大水平位移在30mm内地面不致有明显的裂缝,当最大水平位移在40-50mm内会有可见的地面裂缝,因此,一般的基坑最大水平位移应控制不大于50mm为宜,否则会产生较明显的地面裂缝和沉降,感观上会产生不安全的感觉。
一般较刚性的支护结构,如挡土桩、连续墙加内支撑体系,其位移较小,可控制在30mm之内,对于土钉支护,地质条件较好,且采用超前支护、预应力锚杆等加强措施后可控制较小位移外,一般会大于30mm。 基坑支护是一种特殊的结构方式,具有很多的功能。不同的支护结构适应于不同的水文地质条件,因此,要根据具体问题具体分析,从而选择适用的支护形式。
2.原理:水泥加固土的基本原理是基于水泥加固土的物理化学反应过程,它与混凝土硬化机理不同,由于水泥掺量少,水泥是在具有一定活性介质--土的围绕下进行反应,硬化速度较慢,且作用复杂,水泥水解和水化生成各种水化合物后,有的又发生离子交换和团粒化作用以及凝硬反应,使水泥土强度大大提高。 3.施工流程:
1)桩机定位、对中、调平
放好搅拌桩桩位后,移动搅拌桩机到达指定桩位,对中,调平(用水准仪调平)。
2)调整导向架垂直度
采用经纬仪或吊线锤双向控制导向架垂直度。按设计及规范要求,垂直度小于1.0%桩长。
3)预先拌制浆液
恭城实习报告 篇3
目录
第 1 章 实践概述 ....................................................................... 第 2 章 实践内容 .......................................................................
第3章 认识与收获 .....................................................................
第4章 致谢..................................................................................
1.1实习概况
我上半学期是在平顶山航天建筑工程有限公司实习,下半学期是在漯河坤恒建筑有限公司实习,工地名称是威尼斯小区42#楼42#楼及漯河市金色港湾小区。两个工地都是框架剪力墙结构,在工地上我从事的是资料员的工作。在
平顶山的时候是从地下室开始做的资料,做到主体七层至阁楼的资料,在此过程中我学到了检验批的报验、钢筋原材和焊接的送检、试块和砂浆的送检,及工程上的图纸会审和技术核定单和进度计划的打印工作。
在金色港湾小区工作的这一段时间我学到了很多东西,其中最重要的就是学会了与人相处之道。我来到这个工地的时候已经进行到了主体部分。
实践时间实践时间:20xx 年 9 月 10 日至 20xx 年 4 月27日。 实践目的实习是我们大学生必须经历的过程,是理论与实践想结合的重要方式,使我们在实践中了解社会,在实践中巩固知识,实习又是对我们专业知识的一种检验,它让我们很多在课堂上根本就学不到的知识、技能开阔视野,又能增长见识,为我们走向社会打下坚实的基础,也是我们走向工作岗位的第一步。同时实习也是提高学生政治思想水平、业务素质和动手能力的重要环节,我们通过实习走向社会,接触实物。 对于土建资料员来说,了解熟悉每一个工程的施工工序这是一个非常重要的和关键的,也是一个合格的`土建资料员的必备的素质。因为都知道所有的资料都是紧跟着每一道施工工序产生的。对于现在来说工程材料管理十分的严格。对于土建资料员来说一定要熟悉材料这一块,还有就是材料的取送样。同时加强施工员和技术员的交流。专职资料员其实工作内容是十分的简单,就是收集一些和整理一些工程的资料,其中部分都是好多都是施工员、技术员、测量员提供的。目前我国的整个国内建筑业界的整体的发展是比较混乱,很多不是资料员的工作内容都可能会强加在资料员身上。现在的资料员其实要知道的东西非常全面的。
我在实习过程中担任实习资料员,起初都是师傅手把手教的,什么都不太懂,渐渐的我可以一个人完成了,整理资料的时候要非常仔细,不能出现任何差错。由于是第一次做施工资料,刚开始的时候根本就没有头绪,东问西问才慢慢的上路,一开始的时候许多资料都没按顺序进行编制,后来知道了才慢慢补以前没做的,不管是隐蔽资料、质检资料、质保资料、安全资料等等心理都没有十分明确的概念,每样资料的表格格式都很多,究竟在什么时候该填什么表格都不太清楚,还好相邻的几个项目部和监理等身边的朋友都是有问必答,好多时候都是他们主动提醒我又该做什么资料了我才知道。 经历了大概一年的实习,关于我所做的大概总结为、一:施工现场管理与资料收集
施工管理工作分为三个阶段:即1、施工准备 2、施工阶段 3、竣工验收 ;
「一」施工准备阶段应收集的资料:
1、技木准备 承包合同,工程预算、施工组织设计、图纸会审。
2、现场准备三通一平、工程定位放线及复核、施工许可证申报、质监申报、临时占用道路申报、现场文明施工围蔽、临施建造、材料、机具组织进场。
「二」:施工阶段应收集的资料:
1:质量控制贯沏施工组织设计、制度措施、监督执行规范、规程、工艺标准,贯沏工程质量验收标准,切实执行质量检查和质量验收,做好工序交接捡查验收,隐蔽工程检查验收,防渗漏试水检查验收,变更工程签证,控制材料进场质量,加强施工复核,组织工程质量定期及不定期的质量检查。
2:安全控制贯彻以“予防为主”的安全生产方针,控制五个安全因素(人、材料、机械、方法、环境)其中包括:施工作业安排、用电与防火安全,落实层级安全生产责任制,贯沏安全生产奖惩制度措施,落实安全生产检查制度,组织安全技术交底及安全教育学习。
3:进度控制根据合同工期及施工组织设计,分阶段编制施工进度作业计划,及时检查计划进度,及时调整计划,协调土建与专业施工的协作配合。
4:成本控制及时做好经济签证,贯沏降低成本措施,优化进度计划,优化劳动力,严格控制材料进场数量及质量,材料发放实行限额领料,加强施工放线复核,
做到事前控制质量,减少事后返工损失,掌握经济索赔技巧,及签证索赔,减少经济损失。
5:文明施工施工现场场容管理
6:现场料具管理包括:生产工具(做好发放与回收)、现场材料(施工平面布置图分类堆放并加标色),周转料(分类堆放)。
「 三」:竣工验收阶段
1:技术资料整理组编 包括:施工日志、变更工程、施工验收及检查记录,材料试验报告,质量检查验收记录,资料应及时记录及时签证及时积累,及时整理。(技术资料是甲方用作核对结算的依据,不容忽视。)
2:竣工工程予验收捡查组织竣工工程予检验收,检查验收前工程遗留未完善的工程手尾,及时处理,为竣工验收创造条件。
3:工程竣工验收备案(房屋建筑工程和市政基础设施工程竣工验收备案管理暂行办法)规定:建设单位办理工程竣工验收备案应提交以下材料:
(1):工程竣工验收备案表(房屋建筑工程和市政基础设施工程竣工验收备案表) 「2」 :工程竣工验收报告
「3」:法律、行政法规规定应当由规划、公交消防、环保等部门出具的认可文件或者准许使用文件。
「4」:施工单位签署的工程质量保修书;
「5」:法规、规章规定必须提供的其他文件;
「6」:商品住宅还应当提交《住宅质量保证书》和《住宅使用说明书》。 4:竣工工程验收
工地上施工技术资料按其性质分为七类:
第一类:建筑工程法定建设程序必备文件;
第二类:综合管理资料;
第三类:工程质量控制资料 包括:验收资料 施工菅理资料 产品质量证明文件 检验报告 施工记录及检测报告
第四类:工程安全和功能检验资料及主要功能抽查记录;
第五类:检验批质量验收纪录;
第六类:施工日志;
第七类:竣工图;
三:施工组织设计的编制:
施工组织设计是指导施工准备和组织施工的全面性的技术、经济文件,是指导现场施工的准则;编制施工组织设计必须贯彻统筹规划,科学地组织施工,建立正常的生产秩序,充分利用空间,争取时间,采用先进施工技术,用最少的人力和财力取得最佳的经济效果,以建造出质量优良的工程。施工组织设计是工程施工施工前应编制好的施工技术管理的一项重要的综合技术管理文件,文件必须经过技术审批责任人签名后方能生效。
单位工程施工组织设计内容:
目录 一、工程概况 二、施工管理架构 三、施工总进度计划 四、施工平面布置1:施工平面布置2:施工用水平面布置3:施工用电平面布置五、主要施工设置及机具配备 六、主要工程量及工料分析 七、主要资源及计划 八、施工方法 (一)施工顺序(二)基础工程 (三)土方工程 (四)地下室施工(五)±0.00以上主体工程施工(六)天面防水及隔热层施工(七)装饰工程施工 九、外脚手架搭设及安全防护 十、重直运输 十一、建筑物垂直度控制 十二、质量技术措施 十三、安全技术措施 十四、夏、冬、雨季技术措施 十五、文明施工措施 十
六、防火、用电安全技术措施 十七、夜间施工措施 十八、降低成本技术措施 十
九、产品保护
施工方案内容:
1、工程概况和特点 2、施工程序和方法 3、施工进度安排 4、施工布置 5、劳动力、构配件、机具、材料计划 6、质量保证措施 7、安全措施
四:施工日志与施工纪录填写
(一)现场施工关键资料-----施工日志
施工日志是在建筑工程整个施工阶段有关施工活动(包括施工组织管理和施工技术)和现场情况变化的综合性纪录,也是施工技术人员处理施工问题的备忘录和总结施工管理经验的基本素材。
主要内容: 1、当日气候实况; 2、施工形象进度; 3、资源进退场记录及使用情况
4、有关工程技术文件的收发及文件内容摘要; 5、有关工程技术会议生产会议的决定内容摘要; 6、重大技术问题、安全问题的处理决定及贯沏执行情况; 7、现场施工记录;技术交底; 8、技术安全的培训教育记录(如:工人进埸安全教